Does FOAK Project Size Matter?

3–5 minutes

I would have really liked to say otherwise, but in my experience in helping various First-of-a-Kind (FOAK) cleantech and energy projects, I have seen that size of a project does matter. Financing these early stage commercial scale projects is really challenging as investors are unwilling to take the risk of uncertainty which is the nature of any FOAK project. Even if technical aspects are resolved, integration of multiple licensors and contracting is generally not resolved, making these FOAK projects difficult to scale-up.

There are several aspects which make the smaller projects look unviable to begin with as they might not give the required return on investment, and the product could be more expensive per unit, thus making it even more difficult to get offtake agreements. Many project developers then end up choosing a larger project to give better return on investment.

But it is not as black and white as that. There are several aspects which could favour much smaller FOAK commercial scale project when a new industry is being developed. The list below shows some of the advantages and disadvantages of large and small FOAK projects.

Given the very early nature of FOAK projects, apart from technology, there are other immature aspects such as supply chains, operating procedures, maintenance cycles, and commercial structures, which all need to be better understood and lessons learnt. When a new technology is scaled, not only the plant capacity is scaled up, but all uncertain aspects need to be scaled as well along with it adding to the overall cost of financing. A large FOAK project concentrates that uncertainty into a single, irreversible capital decision. If assumptions prove wrong, the consequences are expensive.

A small FOAK project on the other hand gives the ability to learn and be flexible, even at a slightly higher unit cost and smaller total returns. But it requires less capital, carries lower investor exposure, and is relatively easier to insure and finance. There is possibility to secure smaller, more realistic offtake agreements, might be able to source feedstock more locally and very importantly can be built faster. Smaller facilities create room for the team to learn from a real commercial scale project. They allow teams to identify bottlenecks, refine processes, optimise designs, improve vendor performance, develop new supply chain, and validate cost assumptions in real conditions. And most importantly if risk is shared, the overall impact of things going wrong is minimised, which is what all stakeholders are concerned about.

In early stages, the first facility not only produces a product, but also reliable performance data, cost validation, bankability benchmarks, operational credibility, investor confidence, which all can be later sold and true economies of scale benefits obtained from subsequent facilities. The improved design and integration aspects, optimised supply chain, better and standardised construction methods can all be shared and sold to third parties if necessary. These could be the real revenue generators for the investors. The additional value generated could allow the initial small project investor to even licence some of these to others building larger projects in various geographies in the future.

I would say a larger project is more appropriate when the technology is mature, supply chains are established and there is demand for the product, but those conditions can only be developed with time for new technologies, even with government mandates, subsidies and revenue guarantees. In emerging cleantech and new energy industries, learning should be more valued than early economies of scale efficiency. I feel starting small allows all stakeholders to help each other and allows learning to happen by distributing the risk across all aspects and parties involved, instead of only the large capital taking all the risk.

Additional Points:

  • I have not specified any technology or industry as these thoughts could be applicable to various FOAK projects. I also have not specified what small and large mean and left that to be discussed on a case by case basis for specific industry, depending on the market and risk appetite.
  • To help with initial investment decisions, larger projects could be designed in such a way that they could be developed in phases or train by train approach (the oil & gas industry has been doing that for decades). Lessons learned in early phases could be incorporated in subsequent phases or trains.
  • The smaller size investment could be more suitable for multiple stakeholders to participate as the overall risk when shared would become small. This is not the case if the overall investment is large to start with.
  • Also, smaller investments could be more palatable for smaller financial assets, funds and portfolio managers, who want to get involved in sustainability and energy transition projects. They will also be perceived as lower risk in large financial portfolios.

This thought-piece is suitable for project developers, technology developers, financers & investors, policy makers, and all other stakeholders trying to navigate the challenge of scaling up energy transition projects. Hope this is helpful!

Risk Analysis in Estimating: do-it-yourself (DIY) Monte-Carlo Simulation

5–7 minutes

No matter what class of estimate it is, every estimator makes his or her slightly different assumptions based on their own experience. An estimate is finally an opinion of a particular estimator. Some estimators tend to be pessimistic in every assumption, factor, historic data they use, ending up with a very conservative (i.e. high) overall estimate. For the same technical inputs, which might themselves not be perfect, another estimator might make optimistic assumptions for individual elements of the project, which might make the overall estimate very low. In both cases, the estimator is likely to add a contingency to their estimate.

Most often, the assumptions made by individual estimators are not transparent as they are generally not properly recorded or documented. Besides this, the decision-maker is usually given only one estimate from an individual estimator to look at, which does not give them the option to question or critique the possible range of the overall estimate.

If somehow the same estimate could be done by multiple estimators, and all those estimates were tabulated together, we would get a range of estimates, with a maximum and a minimum value, which would allow everyone to understand the possible range of cost outcomes of a future project. But it would be very expensive or nearly impossible to get the project estimated by several estimators at the same time.

But there is a workaround to this! We could instead use MS Excel to do multiple estimates. And not only that, but we could also get Excel to run 5,000 or even 10,000 estimates almost instantaneously (for free!!).

  • This is like predicting 10,000 possible scenarios out of the infinite possibilities (simulating reality by trying to analyse many possibilities).
  • If we could analyse and simply present these 10,000 results, we could in a way say what the likelihood (probability) of success for a particular point estimate would be.
  • This would be better (and more transparent) than trying to present a single number.

Nobody knows the future, so whatever we predict is likely to be wrong; the point is to reduce the amount of error in our predictions. So, instead of trying to produce a correct single number (Point Estimate), I suggest that we generate a reasonable range instead (Range Estimate).

This is called Monte Carlo simulation, and it is a mathematical model of probability analysis. There are various companies selling risk analysis (Monte Carlo simulation) software in the market, but the cost for those tools (toys!) are sometimes not justifiable even within large organisations. But a range estimate would be really useful by allowing decision-makers to understand what contingency would be suitable for a particular estimate and at what risk level are they pitching the overall number.

I have developed something easy and simple to help bring the team together and run these simulations to see what the possible range of the overall estimate could be:

  • Let us say that you come up with a point estimate for the project – say the total is 100
  • And the estimate is built up by adding, say, 20 different items (or more)
  • But each of those different items could have been assigned a different number (within a particular range)
  • The team can come together to understand the assumptions made by the estimators for those individual items, and can together decide an appropriate range for each item

Once those ranges are defined, we could ask Excel to randomly pick any number between those ranges for each of those items (by using the Excel formula “Randbetween”) and add them up to come up with a new estimate, as shown below:

We could do this 10,000 times to come up with 10,000 new estimates. This is how a simple DIY Monte-Carlo simulation model could be made.

Typical results will look like the following:

Interpretation:

  • The first graph plots all the 10,000 estimates (simulations) generated by this method [using a simple scatter graph]
  • Based on these 10,000 simulations, the second graph shows what are the chances of completing a project within the “Point Estimate” value. [this simply plots the Percentiles of all the 10,000 values using a scatter graph]
  • Do note that in a real life situation there is no chance of all possible worst cases happening simultaneously, nor all the best cases can happen for a project. Therefor the total of all the maximums and all the minimums does not make any sense, and the Monte-Carlo results also show that they never occurred within the 10,000 simulations.

The file attached below is the model I have developed as explained here and is a free estimating resource for anybody who wishes to download and use.

This example template file is designed to take up to 50 items in the inputs tab (this is the breakup of the point estimate), with their estimated values and the max-min ranges for each value. The inputs tab is then linked to the Monte-Carlo Results tab where the 10,000 simulations are run by simply pressing “Fn&F9” together on the keyboard. This tab also presents the results in the graphical form presented earlier. If needed, this file can be modified easily to increase the number of items adding up to a total point estimate.

Biomass Power Plant Benchmarking (Open-Source Example)

In one of my past blogs, I developed and shared an open-source benchmarking example for gas and coal fired power plants. I have now developed another open-source benchmarking graph, using internet-based data, for a typical biomass power plant project. I have mostly used news articles giving the total value of the contract and capacity in Megawatt (MW) of the power plant.

The data is tabulated (in the attached Excel file) with links to the various websites for cross-checking purposes. Within the file I have also escalated the contract values to the current year using a nominal escalation factor (which will vary depending on the market conditions). This can be modified to any future year when needed. This gives a feel of what the market has paid for a typical biomass power plant. These are not out-turn costs but initial awarded values and thus should be treated as such. This is not exact but gives an idea.

No two projects are similar in scope, but what this does is to give an opportunity to the reviewers to understand any special / specific requirements of a project which might make the current project estimate different (like additional fuel conditioning, remote location, additional transmission lines, piling requirement, etc.). The overall plant cost will also vary based on the technology used, quality of fuel used, efficiency of the plant etc.

Also to be noted is that this is only an EPC cost and any Pre-FEED, FEED, other Owner’s costs, service agreements, operation & maintenance costs are to be added separately as needed.

This can be used in addition to or in the absence of any in-house or any third-party benchmarking data. This can be easily shared with anybody and can be used as a cross-check of the detailed biomass power plant estimate at a $/MW level.

The graph is also suitable for coming up with quick order of magnitude estimates for bid / no-bid analysis, initial project sanctions, bid evaluations, etc.

The graph shows the typical trend of reducing unit cost for larger capacity plants.

I have just done some research to show what can be possible with freely available data and so the graph is not considered comprehensive and can be enhanced with more data points if further research is undertaken. Location / area specific graphs can also be generated if enough data points could be gathered.

Feel free to use this as you see fit with or without modifications.


Economic Challenges in Expanding Renewable Power Deployment – An Essay

Abstract

To be able to control the climate crisis and limit the global temperature rise, sustainable renewable energy projects will need to be deployed at a much faster and larger scale from where they currently are in the power generation mix. Apart from the technical challenges, this required renewable energy generation growth faces considerable economic challenges like supply chain issues, high initial investment required, global energy poverty, low return on investment, competition for natural resources like land, trained labour shortages, waste management, changing global trade dynamics, requirement for even higher investments in associated infrastructure for transmission and storage, etc., to list a few. These are explained in detail within this essay. A lot of research is currently ongoing to suggest urgent changes in policies, to help mitigate these challenges, to be implemented by governments at a national level as well as collaboratively at an international level. Some of those policy recommendations are highlighted in this essay.

Introduction

Currently the share of renewables is nearly 29% of electricity generation globally. But to achieve the 2050 net-zero goal to limit global warming to 1.5 degrees above pre-industrial level, re-affirmed recently during various COP meetings, several countries agreed that renewable power needs to increase significantly in the next decade to nearly 60% of global generation mix. Even though the science has developed significantly, scaling up renewables have several economic challenges which needs to be understood and suitably mitigated if we want to successfully combat the climate crisis.

Economic Challenges

Supply chain issue for raw material is a major concern. Critical metals like Nickel, Lithium, Cobalt, etc. are important parts of battery technology. Platinum and rare earth metals form the basic components of wind turbines and electrolysers required for the hydrogen economy.  Most of these metals are mined in only handful of countries and most of the refining is currently undertaken by China. This dependence creates a supply chain challenge for the required scale-up of renewables. Geo-political issues, like the currently ongoing Russia-Ukraine war, the recent pandemic related lockdowns, etc., have already substantially increased many raw material prices and could soon counter the past years of reduction in wind and solar project costs.

High Initial Investment required for renewables will increase the cost of supplying electricity in the short term. Increasing renewables in the energy mix also substantially increases the marginal cost per unit of providing peak load electricity as the network operators will then need to pay for maintaining and operating the backup baseload fossil fuel power plants. This also increases the cost of production of other goods and services making them uncompetitive in the global markets.

Energy Poverty is currently emerging as one of the biggest economic challenges for large scale renewable deployment, as some developing economies cannot simply afford such expense. Most of Africa, many developing countries in South America and southeast Asia have this challenge to overcome. After years of disagreement, during the recent COP27 in Egypt, the richer nations have finally agreed for a “Loss and Damage” fund to be created to help developing nations which are most effected by the climate crisis.

Low profit renewable projects are less attractive to large private investors looking to make quick money from their investments. This becomes even more exacerbated when large scale intermittent renewable power sources are added to the grid, which reduces the overall revenue generated by reducing the wholesale electricity price at which the network can sell power to consumers. Whereas the fossil fuel industry, which pays much higher dividends, is generally backed by billionaires, and this is a huge economic issue for the investments required for large scale renewable projects. Some small to medium size renewable project developers have been crowdfunding their projects, which will not be suitable for large scale-up needed in the next decade.

High discount factors are generally used in all economic modelling and analysis for large scale investment decisions, which means assuming high economic growth in terms of increased GDP, which may not be sustainable. Instead, some economists are now suggesting the use of a lower ‘social discount factor’, which considers the investment needed to counter the negative impact of climate change. Using high discount factors increases the LCOE of renewable projects which make them less attractive.

Resource competition is also a challenge in scaling-up of renewable generation. Some renewable projects like solar and onshore wind farms take up a lot of land space, which can compete with agricultural and other industries creating a tension in the local economy.

Another challenge is to grow the corresponding demand for electricity in the other sectors at the same pace, like electrical vehicles and charging points along with large scale investments in suitable grid upgrades to allow for intermittent renewables’ integration. To make large-scale renewable projects economically viable, their curtailment needs to reduce, thus increasing their capacity factors. This means larger investment in connected hydrogen, hydro, battery, and other storage technologies. This is a financial challenge for even the richer economies, with growing cost of living crisis and rising inflation.

Current Global trade dynamics will be impacted by large scale renewable energy development specifically for the fossil fuel exporting countries like Russia and many Middle Eastern countries, whose GDP is heavily dependent on energy trade. Those economies could try to resist this large-scale energy transition.

Trained labour shortage for this fast-growing industry will be another challenge that all economies will have to carefully consider when scaling-up renewable generation. More experienced personnel are reluctant to move out of the fossil fuel industry and new generation seems to be disenchanted with the energy industry in general.

Waste management will become an economic issue with scale-up of the renewable sector in the next decade. The decommissioning costs for old wind turbines and solar panels will need to be understood better, otherwise this is another externality which might conveniently get missed from any economics and the green transition might not remain that green.

Recommendations for Policymakers

To tackle the above indicated economic challenges, the following points are recommended for policymakers.

  • Encourage recycling and investment in the circular economy to tackle the impact of supply chain issues and waste management.
  • Encourage private investments in renewable energy projects by providing tax incentives, risk mitigations measures like government protection for failed projects if trying out new technologies.
  • Governments of richer countries could implement policies to set aside particular percentage of their national GDP to help develop renewable projects in poorer countries, with a realisation that climate change is a global issue, which needs to be funded by people who have. This can happen once governments can start promoting alternative to GDP growth as economic indications of prosperity like the Human Development Index and employ policies like the EU’s ‘Beyond GDP’ initiative.
  • Implement more low carbon Feed-in tariffs, to protect the renewable sector with fixed purchasing pricing even if the wholesale prices fall with increasing renewable penetration.
  • Impose carbon tax on the fossil fuel industry making the renewable projects more attractive.
  • Encourage investments in associated infrastructure like transmission lines, suitable storage, and hydrogen projects.
  • Encourage more collaboration with neighbouring countries, to help build interconnections, thus reducing the cost per unit of renewable power generated.

Conclusion

The predicted global climate crisis is almost upon us, and alternative technologies are being developed to harness natural sustainable energy resources like wind, solar, geothermal, hydro, ocean etc. But a large-scale implementation of renewables faces numerous economic challenges, which can only be resolved by governments of various countries working together and formulating suitable policies. The United Nations 17 sustainable development goals is one such effort which needs to be really converted into national policies.

Print Macro – Automate Generation of Multiple Estimates

I have seen estimators develop several files or tabs to generate various versions of estimates for the same scope where there are several possible technical and commercial solutions. One example of this is when the client wants to a see what the overall cost of a pipeline project would look like if the diameter is varied and or the material cost is varied based on the supply source. In such a case, the alternative estimates are started as mirror images of the initial estimate but are considered separate estimates. The estimator soon ends up handling multiple estimates in various spreadsheets and tabs for minor updates. There is a high chance of making errors and not updating all the estimates accurately.

Alternatively, there can be only one estimate file, with the detailed estimate changing in response to specific technical and cost inputs. There can be an input table with various options (in separate columns) which is linked to the main detailed estimate (one at a time). In this way, any changes are only made once and would be automatically updated for all options, and the estimator will not have to handle multiple estimates or even separate files.

The only apparent drawback with this approach is that the detailed estimate can only be seen one at a time and the summaries and results of the various options cannot be compared. The results of each option may have to be printed manually into another spreadsheet for analysing. This may seem like a laborious process if there are several options to manage.

Alternatively, a very easy excel macro can help automatically print the results, for the various options, into another tab (or another area of the same spreadsheet) for ready analysis.

The macro will simply run the whole estimate repeatedly for each set of inputs provided. It will then print the required results in pre-assigned cells one after the other. In the above example, if the options are 20 different pipeline diameters with varying material unit cost, the macro would simply run the estimate 20 times, printing the overall results (or any breakups if needed), 20 times at a pre-assigned range of cells in the excel file. These results can then be analysed and presented in a tabular or graphical fashion as required.

A typical example macro looks like below:

Print Macro

In this example, the values from cells A10 to C10 (Range command) from the inputs tab are copied into the estimate tab in cells D14 to F14; the results from the estimate tab in range R49 to U49 are then copied in the output tab in the range G8 to J8. The whole process is repeated 20 times (using x as a counter in conjunction with the “Next” command), with inputs being collected from the next row (Offset command) and the estimate being Run and the results being printed in the output tab in the consecutive rows (using the Offset command again).

Steps:

  • This does not need any prior knowledge of macro writing
  • Go to the “Developer” ribbon in Excel -> click “Macro” -> give a name to your macro such as Macro1 and then press “Create”.

        (If the “Developer” button does not appear in the ribbon, go to File-> click “Options” ->          then go to “Customise Ribbon” and select “Developer”)

  • Then write the command like the one shown in the example box above.
  • Make sure you have the correct ranges for inputs and outputs from your estimate file
  • Note that the input and output ranges can be in a single tab and not necessarily in different tabs.
  • Also, they might not be ranges, but single cell references.
  • Also make sure that the tab names are correctly spelled (I have made that mistake several times in the past)
  • The Offset command moves from one input to the next and is also used to print the outputs in consecutive cells (or sets of cells)
  • Save the macro
  • Then Run the macro

The macro should take few minutes to write, and every time there is an update to the estimate, results of all the options can be printed in seconds by just running this macro and any updated analysis can thus be presented almost immediately. One caution here, during any subsequent updates, make sure that the original cells for the inputs and outputs are not changed, and if they have moved, the macro will not automatically update those, and you will have to change those references by editing the macro with the correct cell references.

I have been using this macro (maybe the only macro I use), for more than 10 years now and this has made the multiple estimate preparation and update process much easier and simpler.

In my view, this is one of the simplest ways to automate the generation of multiple estimates using Excel which does not need any knowledge of macro writing.

The in-house benchmarking graphs for various types of piling as shown in the piling blog were generated using this macro. (I cannot upload a macro-enabled file in WordPress. Try it yourself and see if works, and let me know if you have any questions).

A Call for Transparency: Sharing Working Estimate Files

Excel is commonly used to prepare estimates of various kinds. Such estimates may be based on detailed MTOs; they may be higher level factored estimates; or conceptual estimates based on capacity curves. Even when proprietary software is employed, the final summary is most often prepared in Excel for any overall adjustments and presentations as required. Once prepared, discussed, reviewed and finalised, many estimators tend to then supply only a PDF print of the estimate summary to their internal or external clients. Even if an Excel version is requested, some send out a value-only copy (without formulae) of the estimate.

In my opinion, this is not a very friendly way of working. The person receiving the estimate cannot check, review or adjust the estimate in any way as he/she will not have the working Excel version. In my career, I have reviewed many estimates, where the estimate was only given to me in the PDF format. In all those cases, I had to re-create the estimate in order to be able to do the checking and then make suitable adjustments based on the latest requirements and or understanding. If the working Excel file was available, a lot of time could have been saved.

Estimates are only opinions and are always subject to adjustments based on who is looking at them and or what it is being used for. The estimator spends a considerable amount of paid time building up a working estimate file for their clients and there is no good reason for not wanting to share the working file.

I have tried to understand the logic for this behaviour:

  • Many estimators think that they will be giving away something proprietary if they share a working Excel file, i.e. a contractual reason
  • Maybe they think that they will violate some kind of “code” if working Excel files are shared; i.e. a professional standard
  • Or they want the client to come back to them every time any adjustment is needed even if it is minor as they do not trust others to make any adjustments to the estimate; i.e. special expertise argument
  • Another explanation could be that they don’t want the reviewer to probe too much into the makeup of their estimates (i.e. simply poorly referenced estimates – I would very much like to think that this is not very common)

If none of the above is true, then the only other explanation could be just bad practice and inertia which has not been challenged. I would recommend and request all estimators to always share working Excel files so that the receiver can quickly review and understand the estimate and if required make suitable adjustments. This would also generate more confidence in the estimate and promote a transparent culture.

I have made it a habit and practice to always share my working excel files whenever I am issuing an estimate and never faced any difficulties due to this.

Sharing is caring.

Design Optimisation for a Successful Business Case

As per one school of thought, a conceptual estimate in the early stages of any project, is a very high-level number, and can thus be based on very conservative design assumptions and considerations. This approach invariably makes the initial project cost estimate very high, which in turn could jeopardise the business case altogether as it would not be good value for the client’s money.

Some design teams might think that this gives a more robust technical solution during concept work, but if the project does not go ahead for this reason, then the whole exercise is futile in my opinion.

The obvious alternative could be to base the initial design on slightly more optimistic assumptions and considerations. This could then be followed up with design sensitivities for more onerous requirements and / or considerations. This approach then helps the estimating team to come up with a range of estimates during the concept stage with various degree of confidence in the proposed design solutions. This then gives the management a fighting chance to present the business case for the project with varying technical requirements and constraints.

It is quite understandable that the design team would not want to compromise on robustness of design simply to cut costs. That is not what I am suggesting here. I propose a more collaborative and cost-aware approach so that cost-effective but fully defensible designs are proposed at the concept stage with an offer of add-ons for more robust options.

Some possible places to optimise:

  • Total flowrate/ capacity required (during initial stages of any project, even the client’s team members would not be sure what total capacity would be most appropriate. The requirement could be interpreted differently by different parties, for example this can be due to the aspiration of some team members to build in additional capacity for the future. However, this may not have been discussed with the higher management and might require separate funding or sanctioning. In my opinion, it is best to present various capacity cases during concept)
  •  Efficiency of rotating equipment (newer motors, pumps, turbines and compressors are more efficient than sometimes assumed in design calculations based on old project experience and old technology)
  • Design margins for sizing of individual equipment (sometimes the assumptions are conservative)
  • Understanding of available technology for specialist equipment items (there could be alternative technologies in the market which could be more efficient, requiring less utilities & accessories and cost effective to the overall plant design. Depends on the experience of the individual design team members)
  • Material selection (there is sometimes a range of possible materials that could be suitable for a requirement, and the material selection made could be conservative based on more onerous service envisaged in the future)
  • Different and / or simpler designs for specific areas (like utilities, control & automation, protection philosophy, etc.)
  • Possible multi-use of specific equipment (e.g. combining firewater and wash water into a single tank instead of 2 separate tanks)
  • Design life of equipment and overall plant (the client might not initially require a long design life of individual high-cost specialist equipment and could agree to a complete refurbishment or replacement half way through the plant life to help reduce the initial CAPEX spend)
  • Sparing philosophy requirement (client might not need excessive spares to start with and might want to postpone the purchase of the spares during operations)
  • Any assumed pre-investment for future requirements included in the base design (generally in utilities, additional land clearance areas etc.)

Note that these examples are not actually scope related but more to do with basic design assumption made by specific concept design teams. In these examples, the design team might assume what the client needs, without actually giving the client a chance to really opt for the more onerous design requirements. Depending on the choices made, the above examples could together easily add nearly 20-30% cost to the design or sometimes even more.

If the estimator works closely with the design team and understands the various assumptions and quantifies any alternatives, then they should be able to help the team develop a more optimised estimate and present it as a base case. Add-on numbers could then be presented for the various onerous design requirements. This will better help the decision-making process as everybody would then understand what additional technical features they would get if they choose to spend more money.

The estimator has the right skills to act as an interpreter between the design team and the financial decision-makers and can take on the bigger responsibility during the early stages of any project to work closely with the design development team and present the estimate in a way that is more transparent to help the project being better understood and agreed during any stage gate reviews.

Note: These suggestions are based on my own experience and style of working and could be beneficial to other estimating professionals if they choose. Also note that the examples suggested here are very generic and not specific to any industry, and the fundamental concept discussed should be relevant to any industry and project.

This article was published as an opinion piece in May-2019, in the Project Control Professional which is the journal of The Association of Cost Engineers.

Estimating Time Management

Estimating time management has always been an issue in the all estimating departments which affects the quality of estimates being produced. I would like to discuss how an estimator generally plans his estimating work for a project and how we should be approaching it so as to avoid the last minute rush that is generally experienced in all estimating departments.

The following figure shows a typical estimating schedule

The important points to note in the above figure are:

  • There is a long waiting time by the estimating group between the start of the process and when they actually start getting inputs from the various disciplines.
  • Once the inputs come in there is very little time left before the estimate needs to be complete.
  • The management generally reviews the estimate before the last input has come in.
  • The final estimate needs to be submitted very soon after the last input has come in.

Most estimators deal with this typical situation in the following way:

  • The estimator does not start work before the first input starts coming in.
  • The accuracy of the estimate is compromised and reduced; the estimator blames this on the late receipt of inputs.
  • The late inputs, which arrive after the management reviews, are typically not incorporated into the estimate as there is “not enough time” to do so, or added as very high-level order of magnitude estimates in the form of late changes.

I will propose an alternative to this unsatisfactory approach, based on methods which I have been successfully using for the last several years while working as an estimator.

During the kick-off meeting at the start of the project / proposal effort, the estimator will get a fair idea of what the designers are going to design and typically how similar or dissimilar the new design will roughly be to something done by the company in the past. During the long waiting time, before even a single input has come from the disciplines, the estimator can actually complete a detailed estimate based on the available past project information and come up with the as-of-date estimate of the past project. As a lot of time is required by the estimator to gather typical prices from various sources to use in the estimate preparation, that work will have been done during this process. Another important thing, which takes a lot of the estimator’s time, is the formatting, presentation and management approval of the estimate. If based on an old but similar project / proposal information, the managers are usually quite happy to discuss the results of the as-of-date estimate of that old project, comment and advice on it, and review it. This helps in finalising the estimate even before any input has been provided. This brings forward the time generally spent on the activities at the end of the estimating process. Thus, when the inputs do come in, it takes very little time to update the estimate with the revised (or correct) quantities. The approval cycle is also faster as everybody is already familiar with the cost basis.

I have taken this approach even for projects where there was no historical data available, but people were able to give me a fair idea of what the final product would be like, so that I could assume dummy quantities for my format preparation and basic cost information search.

The following are the advantages of such an approach:

  • No last-minute-rush situation, as the work is evenly distributed during the actual time available for an estimate.
  • More time spent on cost database searches and approaching vendors (if required), thus making the cost basis more accurate.
  • More review time available by the managers.
  • More suitable for training new estimators as there is no pressure on the team to complete an estimate thus requiring some experienced estimator to quickly start and finish the estimate when the inputs come in.
  • Frees the experienced estimator’s time to perform a more supervisory role.
  • Gives better understanding of what kind of inputs are required to complete the estimate and could be used to guide the new discipline engineers on the job to formulate their outputs accordingly.
  • Last but not the least, it gives a clearer idea to the managers about the range of the final figure; this helps them to design their selling pitch accordingly.

I would like to argue that managing and utilising the total available time for any estimate is a more sensible approach, which produces accurate and more reliable estimates.

This article formed part of a larger opinion piece published in Nov-2015, in the Project Control Professional which is the journal of The Association of Cost Engineers.

Supplier Quotes for Estimating

One of the important steps during any estimate preparation is obtaining supplier quotations. Some pricing is based on in-house data from past projects or previously obtained budget quotes, but there is generally a requirement to get latest market pricing for high value items to increase the accuracy of any estimate. The time to obtain these quotations is mostly built into the estimate preparation time. On many occasions, this time may appear inadequate and the team could be unsuccessful in obtaining any meaningful and usable quotations to be included in the estimates thus affecting the estimate accuracy.

In this blog, I will first discuss what tends to be the general approach for obtaining quotations at the estimating stage of any project, and then I will propose a method for making this process more efficient to fit with the available estimate preparation time.

One of the issues I have noticed as part of many teams is the format in which the request is sent out to the suppliers. The requirement, scope descriptions, specifications etc. are sent to the supplier without any pricing format / tabulation to be filled. Every supplier thus interprets the client’s requirement in a different way and submits a priced quotation in varying formats. It then takes a long time to understand the overall pricing being quoted by the suppliers, obtain clarifications if required and then normalise the scope to compare them on an equal footing. It is always a challenge to tabulate, compare, analyse and then suitably use the quotes, in the estimate.

I propose that the estimator should support the engineering/ procurement team in developing suitable tabulations of the required scope to be sent to the suppliers. If all the suppliers are given the same price schedule in an Excel format for example, when the prices come in, it would be an easy task for the team to tabulate the submissions from the various bids and compare them against one another. Any duplication of effort would be immediately removed from the system. No time would be wasted in trying to copy each line item and its quoted price into a spreadsheet. Any comparison and further analysis would become much easier. Any adjustment to the scope and quantities would be easy to make as well. It would reduce the time for any clarifications and bid evaluations, thus allowing the estimate preparation to be completed within time and with a high accuracy.


Case in point

Long ago, when I joined an estimating team of a company, I found that the very detailed quotes which we received from various contractors for fabrication of our equipment, varied widely in terms of the format in which they were quoted. This was partly down to us; we as a team were not very clear in our scope description, hence the quotes were also not very clear on what was included. Small things like painting was sometimes missed out from the bids, or it was not clear if the lifting lugs for transportation and site installation were included or not, or if anchor bolts were missed out. The small items when combined did make a difference to the bottom line and the estimates could end up either double dipping on those items or missing them out completely. We had to have several clarifications before we could compare the various bids and it sometimes took weeks or even months. I realised there was a problem and it affected our ability to produce effective estimates in a timely manner. I helped the team develop a simple excel format to go out to the contractors for pricing for any new enquiries and the template included all the information we needed all suitably tabulated. This then made it easy for the various bidders to quote their prices, quick and easy for us to check if everybody quoted all the items, and even easier to compare different bids and then suitably include the costs into the overall estimates. We reduced the overall time from weeks / months to nearly less than a day for the whole exercise once the contractors’ quotes came in.


I have now made it a practice to help any new team I work with, to develop suitable formats to obtain quotes so that it makes it efficient for everybody involved. If you do not do this already, I would highly recommend it.

Attached is a dummy format in excel for reference.

20161026-dummy-price-schedule (free resource)

Owner Vs Contractor Estimates

Depending on who is looking at an estimate and for what purpose, the actual estimate could be different for the apparently same scope or project. For example, owner estimates could be different from a contractor’s estimate.

Generally, when an estimate is prepared by a contractor, it is for a defined scope of work. But when an owner company wants to estimate for its own internal budget approvals, it is for a “Project”. This means that even if an initial scope is defined, there is always a high chance of scope creep during the course of the project sanctioning process. It is not easy to define all the requirements during the initial stages and with time generally more scope is added to the project for completeness. The estimator in the client’s estimating team should thus be able to correctly pitch the overall number to the funding body in order to encompass possible future scope additions. This adds certain challenges to the process of preparing the estimate.

Contractor estimates are generally for bidding purposes or to generate indicative numbers alongside front-end engineering design work; these are related to a particular scope definition. Any change in scope goes through a change management process and could require additional funding. The point is that somebody has to pay that additional amount, and if the client’s original budget did not envisage those changes, then there will be no budget to pay from. This is different from the contingency amount generally added to the estimates for design refinement and other estimate deficiencies for that particular scope.

The contractor’s estimator always tries to prepare the estimate taking into account the entire scope as defined in the “Scope of Work” document. But when an estimator in the client’s team looks at the same document, they need to double check with their own team whether that particular scope will really deliver the project or if additional facilities / scope will be needed to actually complete the work. The answer can be found by understanding the overall process requirement and also from evaluating previous projects of a similar nature. It is worth keeping in mind here that the ultimate body which approves the overall budget, does not approve a scope of work but a project which promises to deliver a product spec of some fashion. It could be a plant which processes a certain capacity of treated water at a particular purity, or certain oil production rate at a particular specification, or generates certain capacity of power, or a pipeline which is able to transfer certain quantity of fluids.

Several additional items might not be in the initial scope or part of a contractor’s estimate but are needed for the overall approval and actual completion of the project. Examples of such items, which should be considered by the estimator in the client’s team are as follows:

  • Owner’s management costs
  • Land costs
  • Social and environmental impact costs (which could be a significant amount for some projects and could also impact the viability of the project)
  • Cost of treating the by-products (which might not be part of the initial scope definition, but is essential to estimate the project cost completely, without which the project would become unviable)
  • Cost of additional utilities like gas or power without which the current project will not deliver
  • Cost of tying into existing facilities or additional peripheral facilities to export the product
  • Cost of additional infrastructure required in the region or the country without which the project could not be completed

It might not be always possible to estimate these items at the initial stages during the funding approval process as proper definition might not be available, thus making the job of the estimator in the owner’s team quite difficult. But a very rough high level assessment of these costs could be useful. Nothing should be actually excluded when getting the overall project sanctioned.

Professionals in this field are aware that generally large projects are approved against competing projects which address the current industry, business, political, environmental and social needs in different ways. Thus giving a complete picture helps the approving bodies with the selection and the decision making as the chances of any future surprises are greatly reduced.

This article was published as an opinion piece in July-2017, in the Project Control Professional which is the journal of The Association of Cost Engineers.